Fixing on the system. |
Installation of the cutting system of selvage. |
Raise the balance weight : the selvage goes forward. |
Lower the balance weight to engage the selvage in the guide rollers. |
The system is ready to run. |
|
|
|
|
|
00'00'' Arrivals of upright reels. |
00'30'' Positionning of the reel holder. |
01'00'' Raising the pallet. |
01'30'' Setting and tightening of the mandrel. |
02'00'' Lowering of the pallet. |
|
|
|
|
|
00'00'' Transport of reel holder along the machine. |
00'30'' Positionning of the reel holder along the machine. |
01'00'' Removal of the telescopic guides. |
01'30'' Move down the holder, take off the fork-lift truck and thrust the reel holder. |
02'00'' Clingfilm passing through and adjustement. The system is ready to run. |